The church building has changed much in the last month. We are so excited to be using it. Here is a photo update of the progress.
Mike, Luis, Dillon and some friends were able to work hard and get the roof on.
The day the roof finished the doors and windows arrived and we were able to have them installed.
With the completion of the roof, doors and windows we were able to hold our first church service in the building. Though far from complete it was really nice to hold a service there.
This week all the plaster on the inside and outside of the church was completed. Now we are working on the final electrical then will move on to tile.